Dear Neighbour,

We are writing to let you know that we will need to carry out works tomorrow, Saturday 22 April, to progress with the removal of the foundations at Mais House.  In accordance with our permitted working hours, this will be between the hours of 8am and 1pm.

 

We would also like to give you 2 week’s notification of a change to the existing hoarding that is required following clarification of the drainage design. Please see the attached diagram which shows the changes.  This hoarding relocation was due to take place later in the programme but has now been brought forward and will take place during the w/c 1 May 2023.

Hoarding changes plan pdf

 