Sydenham Hill Estate Weekly Works - w/c 17 June 2024

Dear Neighbour,


Please find below the activities that are scheduled to take place from the week commencing Monday 17 June 2024 in connection with the Sydenham Hill Estate Redevelopment Project.

Monday 10 – Friday 14 June

Block A:

  • Building the structure to hold concrete on the 4th floor

  • Scaffolding commencement

Block B:

  • Building the structure to hold the concrete for 1st floor

  • Reinforcement to concrete columns

  • Service trenches at sections for water mains installation

Block C:

  • Building the structure to hold the concrete for 2nd floor

All blocks:

  • Perimeter drainage

  • Waterproofing

Otto Close:

  • Groundworks to foundations

Saturday 22 June

Blocks A/B/C:

  • Material reorganisation

  • Groundworks

  • Drainage installation

  • Steel fixing

Noisy works

  • Plant movement (excavators and dumpers)

Deliveries

  • Muck removal lorries in and out of main gate

  • Concrete lorries in and out of the delivery gate

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best wishes,

The Sydenham Hill Project Team

 

 General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

For site emergencies, please contact Lovell on:

  • Andrew Neary 07881 023 254

  • David Olatunji 07340 379305

  • Peter Trainer 077779 992854