Dear Neighbour,
Please find below the activities that are scheduled to take place from the week commencing Monday 6 November 2023 in connection with the Sydenham Hill Estate Redevelopment Project.
Monday 6 November - Friday 10 November
Site cabin installation on Tuesday 7 November
Drainage works to attenuation tank area
Piling mat installation on Block B (see plan for layout showing Blocks A/B/C)
Piling to Block C and A/B
Hoarding painting to Sydenham Hill wall
Footpath closure for drainage works to the south of the attenuation tank area*
Saturday 10 November - Sunday 11 November
No works taking place
Noisy works
Plant movement (excavators and dumpers)
Piling rig and concrete pumping for piling
Deliveries
Muck away lorries in and out of main gate
Concrete delivered in and out of main gate
Note
*As part of the drainage works, we need to again close the pathway by 16-17 Otto Close to carry out the excavation of a manhole. The date is to be confirmed, we will let you know and put up notices with the diversion route.
If you have any queries, please contact us on info@sydenhamhillproject.com
Best wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact Lovell on 020 8731 3800 (0800 030 4690 out of hours)
Alternative numbers:
Tom Chamulak 07977 056104
Peter Trainer 07779 992854