Sydenham Hill Estate Weekly Works - w/c 6 November 2023

Dear Neighbour,

Please find below the activities that are scheduled to take place from the week commencing Monday 6 November 2023 in connection with the Sydenham Hill Estate Redevelopment Project.

Monday 6 November - Friday 10 November

  • Site cabin installation on Tuesday 7 November

  • Drainage works to attenuation tank area

  • Piling mat installation on Block B (see plan for layout showing Blocks A/B/C)

  • Piling to Block C and A/B

  • Hoarding painting to Sydenham Hill wall

  • Footpath closure for drainage works to the south of the attenuation tank area*

Saturday 10 November - Sunday 11 November

  • No works taking place

Noisy works

  • Plant movement (excavators and dumpers)

  • Piling rig and concrete pumping for piling

Deliveries

  • Muck away lorries in and out of main gate

  • Concrete delivered in and out of main gate

Note

  • *As part of the drainage works, we need to again close the pathway by 16-17 Otto Close to carry out the excavation of a manhole. The date is to be confirmed, we will let you know and put up notices with the diversion route.

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best wishes,

The Sydenham Hill Project Team

 

 General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

For site emergencies, please contact Lovell on 020 8731 3800 (0800 030 4690 out of hours)

Alternative numbers:

Tom Chamulak 07977 056104

Peter Trainer 07779 992854

Plan showing Blocks A, B & C