Sydenham Hill Estate Weekly Works - w/c 13 November 2023

Dear Neighbour,

Please find below the activities that are scheduled to take place from the week commencing Monday 13 November 2023 in connection with the Sydenham Hill Estate Redevelopment Project.

Monday 13 November - Friday 17 November  

  • Site cabin commissioning

  • Green route installed to site cabins from the turnstile

  • Drainage works to attenuation tank area

  • Piling mat installation on Block B (see plan for layout showing Blocks A/B/C)

  • Piling to Block B

  • Hoarding painting to Sydenham Hill wall

  • Footpath closure for drainage works to the south of the attenuation tank area*

  • Possible removal of temporary site cabins from Otto Close

Saturday 18 November - Sunday 19 November

  • No works taking place

Noisy works

  • Plant movement (excavators and dumpers)

  • Piling rig and concrete pumping for piling, roller for pile mat

Deliveries

  • Muck away lorries in and out of main gate

  • Concrete delivered in and out of main gate

Note

  • *As part of the drainage works, we need to again close the pathway by 16-17 Otto Close to carry out the excavation of a manhole. The date is to be confirmed, we will let you know and put up notices with the diversion route.

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best wishes,

The Sydenham Hill Project Team

 

 General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

For site emergencies, please contact Lovell on 020 8731 3800 (0800 030 4690 out of hours)

Alternative numbers:

Tom Chamulak 07977 056104

Peter Trainer 07779 992854

Plan showing Blocks A, B & C