Dear Neighbour,
Please find below the activities that are scheduled to take place from the week commencing Monday 20 November 2023 in connection with the Sydenham Hill Estate Redevelopment Project.
Monday 20 November - Friday 24 November
Site cabin commissioning
Green route installed to site cabins from the turnstile
Drainage works to attenuation tank area
Piling to Block B
Hoarding painting to Sydenham Hill wall
Saturday 25 November - Sunday 26 November
No works taking place
Noisy works
Plant movement (excavators and dumpers)
Piling rig and concrete pumping for piling, roller for pile mat
Deliveries
Muck away lorries in and out of main gate
Concrete delivered in and out of main gate
If you have any queries, please contact us on info@sydenhamhillproject.com
Best wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact Lovell on 020 8731 3800 (0800 030 4690 out of hours)
Alternative numbers:
Tom Chamulak 07977 056104
Peter Trainer 07779 992854