Dear Neighbour,
Please find below the activities that are scheduled to take place from the week commencing Monday 27 November 2023 in connection with the Sydenham Hill Estate Redevelopment Project.
Monday 27 November - Friday 1 December
Green route installed to site cabins from the turnstile
Piling to Block B
Pile testing
Pile cropping and pile caps to Block C
Tower crane base installation
Hoarding painting to Sydenham Hill wall
Saturday 2 December - Sunday 3 December
No works taking place
Noisy works
Plant movement (excavators and dumpers)
Piling rig and concrete pumping for piling, roller for pile mat
Deliveries
Muck away lorries in and out of main gate
Concrete delivered in and out of main gate
If you have any queries, please contact us on info@sydenhamhillproject.com
Best wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00