Sydenham Hill Estate Weekly Works - w/c 4 December 2023

Dear Neighbour,

Please find below the activities that are scheduled to take place from the week commencing Monday 4 December 2023 in connection with the Sydenham Hill Estate Redevelopment Project.

 

Monday 4 December - Friday 8 December  

  • Piling to Block B

  • Pile testing

  • Pile cropping and pile caps to Block C

  • Tower crane base installation

  • Hoarding painting to Sydenham Hill wall

  • Hoarding works to the delivery road by Castlebar

  • Rebuild the low brick wall by Otto Close pathway

 

Saturday 9 December - Sunday 10 December   

  • No works taking place

Noisy works

  • Plant movement (excavators and dumpers)

  • Piling rig and concrete pumping for piling, roller for pile mat

Deliveries

  • Muck away lorries in and out of main gate

  • Concrete delivered in and out of main gate

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best wishes,

The Sydenham Hill Project Team

 

 General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

For site emergencies, please contact Lovell on 020 8731 3800 (0800 030 4690 out of hours)