Sydenham Hill Estate Weekly Works - w/c 11 December 2023

Dear Neighbour,

Please find below the activities that are scheduled to take place from the week commencing Monday 11 December 2023 in connection with the Sydenham Hill Estate Redevelopment Project.

 

Monday 11 December - Friday 15 December  

  • Pile testing

  • Pile cropping and pile caps to Block C

  • Sitewide drainage works ongoing

  • Delivery road remediation works will commence

 

Saturday 16 December - Sunday 17 December   

  • No works taking place

Noisy works

  • Plant movement (excavators and dumpers)

Deliveries

  • Muck away lorries in and out of main gate

  • Concrete delivered in and out of main gate

Note

  • Please note that the tower crane installation is due to take place on Wednesday 20 – Thursday 21 December.

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best wishes,

The Sydenham Hill Project Team

 

 General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

For site emergencies, please contact Lovell on 020 8731 3800 (0800 030 4690 out of hours)

Alternative numbers:

David Olatuji 07340 379 305

Peter Trainer 07779 992 854