Sydenham Hill Estate Weekly Works - w/c 18 December 2023

Dear Neighbour,

Please find below the activities that are scheduled to take place from the week commencing Monday 18 December 2023 in connection with the Sydenham Hill Estate Redevelopment Project. The site will close for the Christmas period from lunchtime on Friday 22 December 2023 and will reopen on Tuesday 2 January 2024.

 

Monday 18 December - Friday 22 December  

·         Pile cropping to Block A

·         Sitewide drainage works ongoing

·         Delivery road remediation works

·         Tower Crane (TC1) erection and testing Wednesday 20 - Thursday 21 December*

 

Saturday 23 December – Monday 1 January

·         No works will take place

 

Noisy works

·         Plant movement (excavators and dumpers)

·         Mobile crane to erect TC1 in and out of the main road on Wednesday 20 and Thursday 21 December

 

Deliveries

·         Muck away lorries in and out of main gate

 

*Note

·         Please note that the tower crane needs to be off the road by 7.00am due to highways requirements.  It will therefore be driven onto site at around 6.30am.  It will then be parked, and the engine turned off and no other works will take place until the 8am site operating time.

 

 

If you have any queries, please contact us on info@sydenhamhillproject.com

 

  

Wishing you all the best for Christmas and the New Year,

 

The Sydenham Hill Project Team

 

 

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

For site emergencies, please contact Lovell on 020 8731 3800 (0800 030 4690 out of hours)

Alternative numbers:

·         David Olatunji 07340 379305

·         Peter Trainer 07779 992854

 

If you have any security concerns whilst the site is shut down over the Christmas period, please contact 0845 600 7695