Dear Neighbour,
Please find below the activities that are scheduled to take place from the week commencing Monday 30 October 2023 in connection with the Sydenham Hill Estate Redevelopment Project.
Monday 30 October - Friday 3 November
Ground excavations for piling rig by Block B (Please see attached plan which shows the locations of Blocks A, B & C)
Piling mat finalising at Blocks A and B
Piling in Block C
Drainage works to attenuation tank area
Site cabin bases laid
Hoarding works at Sydenham Hill Road
Saturday 4 November - Sunday 5 November
No works taking place
Noisy works
Plant movement (excavators and dumpers) at Mais House
Piling – there will be whirring and pumping noises from the piling rigs
Deliveries
Muck away lorries in and out of main gate
Concrete delivered in and out of main gate
Note
As part of the drainage works, we need to close the pathway by 16-17 Otto Close to carry out the excavation of a manhole. These works commenced on Friday 27 October. We will reopen the pathway over the weekend and will need to close it again on Monday 30 October.
If you have any queries, please contact us on info@sydenhamhillproject.com
Best wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact Lovell on 020 8731 3800 (0800 030 4690 out of hours)
Alternative numbers:
Tom Chamulak 07977 056104
Peter Trainer 07779 992854