Sydenham Hill Estate Weekly Works - w/c 30 October 2023

Dear Neighbour,

Please find below the activities that are scheduled to take place from the week commencing Monday 30 October 2023 in connection with the Sydenham Hill Estate Redevelopment Project.


Monday 30 October - Friday 3 November

  • Ground excavations for piling rig by Block B (Please see attached plan which shows the locations of Blocks A, B & C)

  • Piling mat finalising at Blocks A and B

  • Piling in Block C

  • Drainage works to attenuation tank area

  • Site cabin bases laid

  • Hoarding works at Sydenham Hill Road

Saturday 4 November - Sunday 5 November

  • No works taking place


Noisy works

  • Plant movement (excavators and dumpers) at Mais House

  • Piling – there will be whirring and pumping noises from the piling rigs


Deliveries

  • Muck away lorries in and out of main gate

  • Concrete delivered in and out of main gate


Note

  • As part of the drainage works, we need to close the pathway by 16-17 Otto Close to carry out the excavation of a manhole. These works commenced on Friday 27 October. We will reopen the pathway over the weekend and will need to close it again on Monday 30 October.


If you have any queries, please contact us on info@sydenhamhillproject.com

 

 Best wishes,

 The Sydenham Hill Project Team

 

 General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

For site emergencies, please contact Lovell on 020 8731 3800 (0800 030 4690 out of hours)

Alternative numbers:

Tom Chamulak 07977 056104

Peter Trainer 07779 992854

Plan showing Blocks A, B & C