Sydenham Hill Estate Weekly Works - w/c 23 October 2023

Dear Neighbour,

 

Please find below the activities that are scheduled to take place from the week commencing Monday 23 October 2023 in connection with the Sydenham Hill Estate Redevelopment Project.

 

Monday 23 October - Friday 27 October  

  • Ground excavations for piling rig by Blocks A and B

  • Drainage works to attenuation tank area

  • Tree facilitation pruning to T48 (end of Block C) and T93 (by turnstile)

  • Hoarding works continuing at Sydenham Hill Road

 

Saturday 28 October - Sunday 29 October

  • No works taking place

 

Noisy works

  • Plant movement (excavators and dumpers) at Mais House

 

Deliveries

  • Muck away lorries in and out of main gate

  • Piling Rig and piling plant deliveries to site at the end of the week

 

Notes

  • Thank you to those who attended our fourth Meet the Contractor Event on Thursday 5 October. The meeting notes have been added to the presentation slides under the ‘Lovell’ tab on the project website: Link here.

  • As part of the drainage works, we will need to close the pathway by 16-17 Otto Close to carry out the excavation of a manhole.  We anticipate this work could take up to 2 days and apologise for the disruption.  Notices will be put up by the pathway with an alternate route when the works are due take place – see plan below/attached.

If you have any queries, please contact us on info@sydenhamhillproject.com

 

 Best wishes,

 The Sydenham Hill Project Team

 

 General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

For site emergencies, please contact Lovell on 020 8731 3800 (0800 030 4690 out of hours)

Alternative numbers:

Tom Chamulak 07977 056104

Peter Trainer 07779 992854