Please find below the activities that are scheduled to take place from the week commencing Monday 16 October 2023 in connection with the Sydenham Hill Estate Redevelopment Project.
Monday 16 October - Friday 20 October
Ground excavations for piling rig by Blocks A and B
Drainage works to attenuation tank area
Digging and installation of two attenuation tanks
Hoarding works at Sydenham Hill Road
Saturday 21 October - Sunday 22 October
No works taking place
Noisy works
Plant movement (excavators and dumpers) at Mais House
Deliveries
Muck away lorries in and out of main gate
Notes
Lovell will be carrying out a fire drill on Monday 16 October at 11am.
Thank you to those who attended our fourth Meet the Contractor Event on Thursday 5 October. The presentation has been added to the ‘Lovell’ tab on the project website: Link here.
As part of the drainage works, we will need to close the pathway by 16-17 Otto Close to carry out the excavation of a manhole. We anticipate this work could take up to 2 days and apologise for the disruption. Notices will be put up by the pathway with an alternate route when the works are due take place – see plan below/attached.
If you have any queries, please contact us on info@sydenhamhillproject.com
Best wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact Lovell on 020 8731 3800 (0800 030 4690 out of hours)
Alternative numbers:
Tom Chamulak 07977 056104
Peter Trainer 07779 992854