Sydenham Hill Estate Weekly Works - w/c 3 April and w/c 10 April

Dear Neighbour

Please find below the activities that are scheduled to take place over the next two weeks in connection with the Sydenham Hill Estate Redevelopment Project.  

Monday 3 April - Thursday 6 April & Tuesday 11 April - Friday 14 April

 Works will include:

  • Continuing hard demolition of Mais House

  • Tree stump grinding and continuing facilitation of pruning works 

  • Bat relocation ongoing in line with demolition works

  • Hoarding relocation around the grove of trees to the southeast of Mais House

  • Hoarding painting

  • Hoarding lighting to be installed in Otto Close walkway

  • Temporary street lighting to be installed in Otto Close.

Friday 7 April – Monday 10 April & Sat 15 April – Sunday 16 April

  • No works scheduled over the weekends or bank holidays.

Notes

  • Following the electrical power outage this week we have assisted the Estates team in investigating the fault and getting the external lights working again.  We understand that electricians from Wates will be on site next week to continue these works.

  • Our arboriculturist and ecologist have visited the site to assess the progress of the tree felling, safeguarding of the remaining trees, and installation of bat houses by our approved professional contractors.

  • Hoarding works and tree protection zones are in place ahead of demolition to Mais House and will continue to be in place ahead of demolition to the garages in Otto Close.

  • We have committed to maximising the use of all wood sourced from the estate, ensuring all usable wood is recovered and reused. This week, we repurposed logs sourced from felled trees within the estate to local Primary School Eliot Bank. The school will be using these to provide seating in their Forest School, where students learn personal, social and technical skills in a natural outdoor environment.

 

Meet the Contractor Event

  • Thank you to those who attended our Meet the Contractor Event on Thursday 23 March.  The slides and a summary of the Q&A session have been uploaded to the project website: www.sydenhamhillproject.com/lovell

Deliveries

  • Demolition tipper lorries

  • One wood lorry per day for timber removal and recycling

  • Tree felling plant and waste away.

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 9:00 to 13:00

For site emergencies, please contact Garfield Williams from Lovell

T: 07721 628436 or 020 8731 3800 (0800 030 4690 out of hours)