Sydenham Hill Estate Weekly Works - w/c 27 March

Dear Neighbour

Please find below the activities that are scheduled to take place from the week commencing Monday 27 March 2023, in connection with the Sydenham Hill Estate Redevelopment Project.

Monday 27 March – Friday 31 March

Works will include:

  • Hoarding relocation around the grove of trees to the southeast of Mais House

  • Continuing hard demolition of Mais House

  • Tree felling works, stump grinding and facilitation pruning works

  • Tree protection fencing continues to be in place to facilitate removal of trees

  • Bat relocation works ongoing in line with demolition works

  • Hoarding works continuing to the back of Otto Close

  • Hoarding painting.

Saturday 1 April – Sunday 2 April

  • No works scheduled.

Notes

  • We have installed 3 monitoring stations on site to monitor vibrations, dust and noise during the demolition and construction period. The limits are set by HSE (Health & Safety Executive), and we will be immediately notified and works will stop if any limits are exceeded.

  • Our arboriculturist and ecologist have visited the site to assess the progress of the tree felling, safeguarding of the remaining trees, and installation of bat houses by our approved professional contractors

  • Hoarding works and tree protection zones are in place ahead of demolition to Mais House and will continue to be in place ahead of demolition to the garages in Otto Close

  • There is ongoing monitoring regarding pest control within our site boundary, a topic brought up by residents at our previous community liaison group meeting. No issues have been identified yet.

Deliveries

  • Demolition tipper lorries

  • One wood lorry per day for timber removal and recycling

  • Tree felling plant and waste away.

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 9:00 to 13:00

For site emergencies, please contact Garfield Williams from Lovell

T: 07721 628436 or 020 8731 3800 (0800 030 4690 out of hours)