Please find below the activities that are scheduled to take place from the week commencing Monday 3 February 2025 in connection with the Sydenham Hill Estate Redevelopment Project.
Monday 3 - Friday 7 February; Saturday 8 February (08.00 - 13.00)
Block A
Brickwork to 3rd floor patterned panel & perimeter snagging
Lift installation ongoing
Plastering ground floor corridors & decorating apartments
Tiling - 1st & 2nd floor bathrooms & kitchens
Kitchen delivery & installation, 2nd & 3rd floor
Installation of internal doors, utility cupboards, switches & lights, 3rd floor
Block B
UKPN fitout works to substation
Perimeter brickwork, 2nd floor
First fix electrics, ground floor
High level mechanical services installation, 2nd floor
Internal walls, 3rd & 4th floor
Blockwork & brickwork to 4th floor roof area
Roof leadwork
Block C
Brickwork, 2nd & 3rd floor
Lift installation
Wall closures, ceiling grid & plastering - lower ground floor
Mechanical & electrical testing & sign off, ground floor
Sprinkler testing, 2nd floor
Pitched roof covering & waterproofing
Otto Close
Joist installation, houses 1-4
Structural steel & roof truss installation, houses 5-7
Brickwork to first floor, 8-11
No large deliveries planned
Notes/Future works
UKPN are on target to finish the electrical connection works before their permit ends on Tuesday 4 February.
Security
The night security guard remains on site. The new shared phone isn’t set up yet, but if you have any issues this weekend, please contact:
Francis: 07404568652 – Friday-Saturday
Ola: 07466993934 – Saturday - Sunday
If you have any queries, please contact us on info@sydenhamhillproject.com
Best Wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact:
Andrew Neary 07436 049 480
Joe Martin 07967 277 400
Hannah Morgan 07769 306 933
Hamid Vafaeifard 07587 103 467
Dion King 07901 737 269
Laury Jancauskas 07502 600 834