Sydenham Hill Estate Weekly Works - w/c 28 May 2024

Dear Neighbour,


Please find below the activities that are scheduled to take place from the week commencing Tuesday 28 May 2024 in connection with the Sydenham Hill Estate Redevelopment Project.

Tuesday 28 May – Friday 31 May (no work on Bank holiday Monday)

Block A:

  • Building retaining wall foundations

  • Perimeter drainage installation

  • Waterproof install ready for splash course

Block B:

  • Cutting down concrete to foundation piles

  • Concrete pour to pile caps, ground floor and substation

  • Reinforcement to concrete foundation piles

  • Ground floor waterproofing

  • Perimeter drainage installation

  • Service trenches at sections for water mains installation

Block C:

  • Cutting down concrete to foundation piles

  • Concrete pour to pile caps

  • Reinforcement to concrete foundation piles

  • Building the structure to hold the concrete for 1st floor/upper ground floor

  • Ground floor waterproofing

Otto Close:

  • Piling

  • Replace Heras fencing with hoarding

Saturday 1 June

  • Material reorganisation

  • Cutting down piles

  • Reinforcement to concrete foundation piles

  • Drainage installation

  • Steel fixing

  • Otto Close: Piling

Noisy works

  • Plant movement (excavators and dumpers)

  • Concrete pumping for piling (Otto Close)

  • Roller for the pile mat (Otto Close)

Deliveries

  • Piling rig – please see note below*

  • Muck removal lorries in and out of main gate

  • Concrete lorries in and out of the delivery gate

Note/works for coming weeks:

  • The piling rig and other vehicles for piling at Otto Close will be coming onto site at approximately 10am on Tuesday 28 May. Otto Close will be blocked for around 2 hours until 12pm to unload the rig and plant.   Traffic marshalls will be present to direct traffic and to facilitate pedestrian access.

  • Foundation works are ongoing for further Lovell welfare cabins. The cabins are due to be delivered in w/c 3/6/24.

Save the Date

  • We will be holding our 5th Meet the Contractor event on Thursday 6 June 2024, 5-7pm in the ball court area.  Please come along and ask any questions you may have for the Lovell team.

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best wishes,

The Sydenham Hill Project Team

 

 General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

For site emergencies, please contact Lovell on:

  • Andrew Neary 07881 023 254

  • David Olatunji 07340 379305

  • Laury Jancauska 07502 600834

  • Peter Trainer 077779 992854