Please find below the activities that are scheduled to take place from the week commencing Monday 3 June 2024 in connection with the Sydenham Hill Estate Redevelopment Project.

Monday 3 – Friday 7 June

Block A:

  • Concrete pour to third floor columns and lift shaft.

  • Building retaining wall foundations

Block B:

  • Concrete pour to ground floor columns and wall.

Block C:

  • Concrete pour to level 2 slab and columns

  • Building the structure to hold the concrete for 1st floor/upper ground floor.

All blocks:

  • Works to lay the perimeter drainage and services to the main buildings and substation.

  • Site welfare cabins installation

Otto Close:

  • Piling

  • Replace Heras fencing with hoarding.

Saturday 8 June

Blocks A/B/C:

  • Material reorganisation

  • Steel fixing

Otto Close:

  • Piling

Noisy works

  • Plant movement (excavators and dumpers)

  • Concrete pumping for piling (Otto Close)

Deliveries

  • Muck removal lorries in and out of main gate

  • Concrete lorries in and out of the delivery gate

Meet the Contractor Event

  • We will be holding our 5th Meet the Contractor event on Thursday 6 June 2024, 5-7pm in the ball court area.  Please come along and ask any questions you may have for the Lovell team.

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best wishes,

The Sydenham Hill Project Team

 

 General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

For site emergencies, please contact Lovell on:

  • Andrew Neary 07881 023 254

  • David Olatunji 07340 379305

  • Laury Jancauska 07502 600834