Dear Neighbour,
Please find below the activities that are scheduled to take place from the week commencing Monday 3 June 2024 in connection with the Sydenham Hill Estate Redevelopment Project.
Monday 3 – Friday 7 June
Block A:
Concrete pour to third floor columns and lift shaft.
Building retaining wall foundations
Block B:
Concrete pour to ground floor columns and wall.
Block C:
Concrete pour to level 2 slab and columns
Building the structure to hold the concrete for 1st floor/upper ground floor.
All blocks:
Works to lay the perimeter drainage and services to the main buildings and substation.
Site welfare cabins installation
Otto Close:
Piling
Replace Heras fencing with hoarding.
Saturday 8 June
Blocks A/B/C:
Material reorganisation
Steel fixing
Otto Close:
Piling
Noisy works
Plant movement (excavators and dumpers)
Concrete pumping for piling (Otto Close)
Deliveries
Muck removal lorries in and out of main gate
Concrete lorries in and out of the delivery gate
Meet the Contractor Event
We will be holding our 5th Meet the Contractor event on Thursday 6 June 2024, 5-7pm in the ball court area. Please come along and ask any questions you may have for the Lovell team.
If you have any queries, please contact us on info@sydenhamhillproject.com
Best wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact Lovell on:
Andrew Neary 07881 023 254
David Olatunji 07340 379305
Laury Jancauska 07502 600834
Peter Trainer 077779 992854