Please find below the activities that are scheduled to take place from the week commencing Monday 26 February 2024 in connection with the Sydenham Hill Estate Redevelopment Project.
Monday 26 – Friday 1 March
Pile cropping to Block A & Block B
Pile caps to Block A & Block C
Ground Beams to Block A
Under slab drainage works at Block A & Block C
Blinding for ground floor slab – Block A
Insulation & waterproofing – Block C
Steel work for the ground floor slab – Block C
Lift core at Block B
Otto Close: Drainage diversion works by 23 Lammas Green
Saturday 2 March - Sunday 3 March
No works will take place
Noisy works
Plant movement (excavators and dumpers)
Deliveries
Muck away lorries in and out of main gate
Concrete lorries in and out of the delivery gate
Note
We held a Meet the Contractor Event on Wednesday 21st February to share a construction update. The presentation from the evening is available to view here or on the website.
If you have any queries, please contact us on info@sydenhamhillproject.com
Best wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact Lovell on 020 8731 3800 (0800 030 4690 out of hours)
Alternative numbers:
David Olatunji 07340 379305
Peter Trainer 07779 992854
Laury Jancauska 07502 600834