Sydenham Hill Estate Weekly Works - w/c 19 February 2024

Dear Neighbour,

 

Please find below the activities that are scheduled to take place from the week commencing Monday 19 February 2024 in connection with the Sydenham Hill Estate Redevelopment Project.

 

Monday 19 – Friday 23 February    

  • Pile caps to Block A & Block C

  • Ground Beams to Block A & Block C

  • Under slab drainage works at Block A & Block C

  • Lift core at Block A & Block C

  • Preparation for ground floor slab at Block C

  • Installation of fence on Sydenham Hill

  • Duct for telecoms installation (see note below)

  • Otto Close: Drainage works, vegetation removal and brick wall removal as per approved listed building consent.

 

Saturday 24 – Sunday 25 February 

  • No works will take place

 

Noisy works

  • Plant movement (excavators and dumpers)

 

Deliveries

  • Otto Close: Earth materials deliveries in and out of gate

  • Muck away lorries in and out of main gate

  • Concrete lorries in and out of the delivery gate

Note

  • We will be installing a duct for telecoms (BT Fibre) by the site entrance to Mais House. The alleyway leading to Sydenham Hill will be traffic managed for half the day while works are carried out.

Meet the Contractor Event

  • We will be holding our next Meet the Contractor Event on Wednesday 21st February at 6.30pm at Lammas Green Community Hall to give you a construction update and answer any questions you may have.  We hope you will be able to join us.

 

Please click here to download the latest Construction Newsletter.

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best wishes,

The Sydenham Hill Project Team

 

 General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

For site emergencies, please contact Lovell on 020 8731 3800 (0800 030 4690 out of hours)

Alternative numbers:

  • David Olatunji 07340 379305

  • Peter Trainer 07779 992854

  • Laury Jancauska 07502 600834