Sydenham Hill Estate Weekly Works - w/c 4 March 2024

Dear Neighbour,

 

Please find below the activities that are scheduled to take place from the week commencing Monday 4 March 2024 in connection with the Sydenham Hill Estate Redevelopment Project.

 

Monday 4 – Friday 8 March    

Block C:          

  • Insulation & waterproofing

  • Formwork

  • Steel work for ground floor slab

  • Pouring of part of ground floor slab

Block A:          

  • Pile cropping & pile caps

  • Ground beams

  • Under slab drainage

  • Blinding for ground floor slab

  • Insulation & waterproofing

  • Formwork

  • Steel work for ground floor slab

  • Pouring of part of ground floor slab

  • Pile cropping to Block A & Block B

Block B:          

  • Pile cropping & pile caps

  • Lift core

Otto Close:     

  • Drainage diversion works by 23 Lammas Green

 

Saturday 9 – Sunday 10 March 

  • No works will take place

 

Noisy works

  • Plant movement (excavators and dumpers)

 

Deliveries

  • Muck away lorries in and out of main gate

  • Concrete lorries in and out of the delivery gate

 

Note

Please note that we have upgraded our security system to monitor night-time activity on the site which includes an alarm and automated voice in the event of any site intruders.  We do hope that this doesn’t take place, however it is important that these measures are put in place for public safety.

 

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best wishes,

The Sydenham Hill Project Team

 

 General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

For site emergencies, please contact Lovell on 020 8731 3800 (0800 030 4690 out of hours)

Alternative numbers:

  • David Olatunji 07340 379305

  • Peter Trainer 07779 992854

  • Laury Jancauska 07502 600834