Please find below the activities that are scheduled to take place from the week commencing Monday 4 March 2024 in connection with the Sydenham Hill Estate Redevelopment Project.
Monday 4 – Friday 8 March
Block C:
Insulation & waterproofing
Formwork
Steel work for ground floor slab
Pouring of part of ground floor slab
Block A:
Pile cropping & pile caps
Ground beams
Under slab drainage
Blinding for ground floor slab
Insulation & waterproofing
Formwork
Steel work for ground floor slab
Pouring of part of ground floor slab
Pile cropping to Block A & Block B
Block B:
Pile cropping & pile caps
Lift core
Otto Close:
Drainage diversion works by 23 Lammas Green
Saturday 9 – Sunday 10 March
No works will take place
Noisy works
Plant movement (excavators and dumpers)
Deliveries
Muck away lorries in and out of main gate
Concrete lorries in and out of the delivery gate
Note
Please note that we have upgraded our security system to monitor night-time activity on the site which includes an alarm and automated voice in the event of any site intruders. We do hope that this doesn’t take place, however it is important that these measures are put in place for public safety.
If you have any queries, please contact us on info@sydenhamhillproject.com
Best wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact Lovell on 020 8731 3800 (0800 030 4690 out of hours)
Alternative numbers:
David Olatunji 07340 379305
Peter Trainer 07779 992854
Laury Jancauska 07502 600834