Sydenham Hill Estate Weekly Works - w/c 24 July 2023

Dear Neighbour,

Please find below the activities that are scheduled to take place from the week commencing Monday 24 July 2023 in connection with the Sydenham Hill Estate Redevelopment Project.

Monday 24 July – Friday 28 July

  • Groundwork investigations and surveys at Mais House may continue

  • Hoarding realignment – to the south of Mais House near Otto Close residents and the path just below the site (refer to the attachment)

  • Hoarding installed to the back garden of 23 Lammas Green

  • Tree facilitation pruning works to both Mais House and Otto Close

  • Toilet block being delivered to Mais House

Saturday 29 July – Sunday 30 July

  • No works planned

Note

  • As noted last week, the City Corporation has instructed surveyors Calford Seaden to carry out condition surveys at properties bordering the development site and they have sent out letters to those properties.   They carried out some surveys this week and will be back on Thursday 25 and Friday 26 July between 10am and 3pm.  If you have any queries, please contact Alison: ahann@calfordseaden.com

Deliveries

  • Toilet block and hoarding materials

 

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

For site emergencies, please contact Lovell on 020 8731 3800 (0800 030 4690 out of hours) Alternative numbers:        

John Weller 073932 49667

Peter Trainer 07779 992854

Best wishes,

Sydenham Hill Project Team