Dear Neighbour,
Please find below the activities that are scheduled to take place from the week commencing Monday 22 May 2023, in connection with the Sydenham Hill Estate Redevelopment Project.
We would like to inform you that there will be minimal on-site activity in the coming weeks. During this period, the primary focus will be on conducting surveys to gather additional information for the design process.
Monday 22nd May – Friday 26th May
Works will include:
Exploratory surveys at Otto Close ball court
Painting of the hoarding
Saturday 20th May – Sunday 21st May
No works planned to take place
Note
The ball court area will be out of use whilst we conduct surveys throughout the week.
Deliveries
None planned during the week
Please note that though there won’t be any works taking place on Saturday 20 May, contractors will be picking up of one excavator from Mais House tomorrow morning. This should take approximately 30 minutes.
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact Lovell on 020 8731 3800 (0800 030 4690 out of hours)
Alternative numbers:
Thomas Farquhar 07442 83565
Peter Trainer 07779 992854
John Weller 073932 49667