Sydenham Hill Estate Weekly Works Update: w/c Monday 20 January 2025

Dear Neighbour,

Please find below the activities that are scheduled to take place from the week commencing Monday 20 January 2025 in connection with the Sydenham Hill Estate Redevelopment Project.

Monday 20 -Friday 24 January, Saturday 25 January (08.00-13.00)

 Block A

  • Brickwork to 3rd patterned panel & perimeter snagging

  • Lift installation

  • Tiling - ground floor apartments

  • Kitchen delivery for ground & first floor, installation to follow

  • Boarding of corridors and Lights, 1st floor

  • Internal doors & skirting, 2nd floor

  • Baths & kitchen plumbing, lights & switches, 2nd floor

  • Plastering & mist coating 3rd floor

Block B

  • Internal blockwork, ground floor by staircase

  • Perimeter brickwork, 2nd floor

  • Internal walls, 2nd - 3rd floor

  • Blockwork & brickwork to 4th floor roof area

  • Screed, party walls & masonry support, 5th floor

  • External boarding & windows, 6th floor

  • Roof waterproofing

Block C

  • Brickwork, 2nd & 3rd floor

  • Loadout of materials for lift installation

  • Wall insulation, ductwork & service sign off - lower ground floor

  • Mechanical & electrical testing & sign off, ground floor

  • Lagging to copper pipes, 2nd & 3rd floor

  • Pitched roof covering to 3rd & 4th floor roof

  • Roof blockwork, brickwork & waterproofing

Otto Close

  • Blockwork to 2nd floor, houses 1-4

  • Installing wall plate and structural steel - target roof truss installation, houses 5-7

  • Building blockwork wall, 1st floor, houses 8-11

  • No large deliveries planned

Notes/Future works

  • UKPN will be returning to complete the electrical connection works, which is likely to involve a lane closure on Sydenham Hill. They have a permit from Wednesday 22 January until Tuesday 4 February. We apologise for the disruption this will cause. We understand that the previous lights (for Thames Water connection) were faulty, so we will ask UKPN/TFL to provide contact information should this happen again and will update you when we know the confirmed road closure dates.

Security

  • We now have a security guard monitoring the site over the evenings and weekends. If you need to contact him (i.e. he can access the fuse board if the estate lighting trips), please call or message him on:

    Ajani Fatai Oguntope 07453 270939

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best Wishes,

The Sydenham Hill Project Team

 

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

 For site emergencies, please contact:

Andrew Neary 07436 049 480

Joe Martin                   07967 277 400

Hannah Morgan          07769 306 933

Hamid Vafaeifard        07587 103 467

Dion King                     07901 737 269

Laury Jancauskas         07502 600 834