Dear Neighbour,
Please find below the activities that are scheduled to take place from the week commencing Monday 13 January 2025 in connection with the Sydenham Hill Estate Redevelopment Project.
Monday 13 -Friday 17 January, Saturday 18 January (08.00-13.00)
Block A
Brickwork to 3rd & 4th floor
Lift installation
Tiling & lino - ground floor apartments
Boarding of corridors, doors & skirting, 1st floor
Baths & kitchen plumbing, lights & switches, 2nd floor
Plastering & mist coating, 3rd floor
Installation of duct to roof void
Block B
Perimeter brickwork, 2nd floor
Internal walls, 1st - 2nd floor
Blockwork & brickwork to 4th floor roof
Screed to 5th floor
Party walls & masonry support, 5th floor
External boarding & windows, 6th floor
Roof waterproofing
Block C
Brickwork, 2nd & 3rd floor
Loadout of materials for lift installation
Wall insulation & ductwork signoff - lower ground floor
Mechanical & electrical testing & sign off, ground floor
Mechanical & electrical services first fix, 2nd & 3rd floor
Pitched roof covering to 3rd & 4th floor roof
Roof blockwork, brickwork & waterproofing
Otto Close
Scaffold birdcage, level 1-2, houses 1-4
Brickwork & blockwork to level 1.5 and scaffold from levels 1-2, houses 5-7
Brickwork & blockwork to levels 1 - 1.5, houses 8-11
Scaffold deliveries
Deliveries
There will be further scaffold deliveries in Otto Close throughout the week which could take up to 2 hours to offload.
Notes/Future works
The UKPN electrical connection works on Sydenham Hill have commenced and will last for a few weeks - we will let you know when these are nearing completion.
If you have any queries, please contact us on info@sydenhamhillproject.com
Best Wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00