Sydenham Hill Estate Weekly Works Update: w/c Monday 6 January 2025

Dear Neighbour,

 

We would like to wish you all a very Happy New Year.

Please find below the activities that are scheduled to take place from the week commencing Monday 6 January 2025 in connection with the Sydenham Hill Estate Redevelopment Project.

Monday 6 -Friday 10 January, Saturday 11 January (08.00-13.00)

 Block A

  • Brickwork to 3rd & 4th floor

  • Lift installation

  • Tiling - ground floor bathrooms

  • Boarding of corridors & joinery installation, 1st floor

  • Baths & kitchen plumbing, lights & switches - 1st & 2nd floor

  • Mist coating, 2nd floor

  • Ceiling boards & plastering, 3rd floor

  • Brickwork and blockwork to roof ongoing

  • Installation of duct to roof void

Block B

  • Perimeter brickwork, 2nd floor

  • Internal walls, 1st - 2nd floor

  • Screed to 4th floor

  • Party walls & masonry support, 5th floor

  • External boarding & windows, 5th - 6th floor

  • Roof blockwork (4th floor) & waterproofing (6th floor)

Block C

  • Brickwork, 2nd & 3rd floor

  • Wall insulation & ductwork - lower ground floor

  • Mechanical & electrical testing & sign off, ground floor

  • Mechanical & electrical services first fix, 2nd & 3rd floor

  • Roof blockwork & brickwork (4th floor) & waterproofing (3rd floor)

Otto Close

  • Scaffold birdcage, 1st & 2nd floor, houses 1-4

  • Brickwork & blockwork to 1st floor and target scaffold to 2nd floor, houses 5-7

  • Brickwork & blockwork to 1st floor, houses 8-11

  • Scaffold deliveries - *see below

Deliveries

  •  There is a scaffold delivery expected in Otto Close around 9am on Tuesday 7 January which is expected to take around 2 hours to offload.

Notes/Future works

  • We have been advised by UKPN that electrical connection works on Sydenham Hill will start from 8 January 2025 and will involve a single lane road closure.

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best Wishes,

The Sydenham Hill Project Team

 

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

 For site emergencies, please contact:

Andrew Neary             07436 049 480

Joe Martin                   07967 277 400

Hannah Morgan          07769 306 933

Hamid Vafaeifard        07587 103 467

Dion King                     07901 737 269

Laury Jancauskas         07502 600 834