Dear Neighbour,
Please find below the activities that are scheduled to take place from the week commencing Monday 18 September 2023, in connection with the Sydenham Hill Estate Redevelopment Project.
Monday 18 September – Friday 22 September
Site control surveying and marking out of grids
Set up of welfare cabins at Otto Close
Setting up base stations
Site clean-up and signage in preparation for start of works
Saturday 23 September – Sunday 24 September
No works planned to take place.
Deliveries
Cabins and storage container delivered for Otto Close
Save the Date
We will be holding our fourth Meet the Contractor Event on Thursday 5th October to give you a construction update and answer any questions you may have.
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
If you have any queries, please contact us on info@sydenhamhillproject.com
Best wishes,
The Sydenham Hill Project Team
For site emergencies, please contact Lovell on 020 8731 3800 (0800 030 4690 out of hours)
Alternative numbers:
Tom Chamulak 07977 056104
Peter Trainer 07779 992854