Please find below the activities that are scheduled to take place from the week commencing Monday 17 February 2025 in connection with the Sydenham Hill Estate Redevelopment Project.
Monday 17 - Friday 21 February; Saturday 22 February (08.00 - 13.00)
Block A
Brickwork snagging & cleaning
Scaffold Strike & window cleaning down to 3rd floor
Lift installation ongoing
Plastering & boarding of corridors
Final decoration & snagging to ground & 1st floor apartments
Tiling - 3rd floor bathrooms & kitchens
Utility Cupboards & balcony sills, 3rd floor
Paving and stones to roof
Mechanical pipework installation in atrium
Block B
Perimeter brickwork, 2nd floor
High level mechanical services installation, 3rd floor
Internal walls & brickwork, 5th floor
Ductwork, 6th floor
Scaffold bridge to 4th floor roof area
Roof truss delivery & installation to 4th floor roof
Block C
Installation of plant to plantroom
Brickwork, 2nd & 3rd floor
Lift installation ongoing
Ductwork & ceiling grid, lower ground floor
Mechanical & electrical testing & sign off, ground floor
Plastering - 1st floor
Sprinkler testing, 3rd floor
Pitched roof covering to 3rd/4th floor
Fascia and gutter installation to lower roof (3rd floor)
Otto Close
Blockwork to 2nd floor, houses 1-4
Roof truss and dorma installation, houses 5-7
Joist installation for 2nd floor, houses 8-11
Security
The night security guard remains on site and the new phone is set up. If you have any issues overnight or over the weekend, please call: 07759 833 036
If you have any queries, please contact us on info@sydenhamhillproject.com
Best Wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact:
Andrew Neary 07436 049 480
Hannah Morgan 07769 306 933
Hamid Vafaeifard 07587 103 467
Dion King 07901 737 269
Laury Jancauskas 07502 600 834
Security 07759 833 036