Sydenham Hill Estate Weekly Works Update: w/c Monday 24 February 2025

Dear Neighbour,

Please find below the activities that are scheduled to take place from the week commencing Monday 24 February 2025 in connection with the Sydenham Hill Estate Redevelopment Project.

Monday 24 - Friday 28 February; Saturday 1 March (08.00 - 13.00)

 Block A

  • Brickwork snagging & cleaning

  • Scaffold Strike & window cleaning down to 2nd floor

  • Lift installation ongoing

  • Plastering & boarding of corridors

  • Decoration of ground & 1st floor apartments

  • Appliance delivery & installation, 1st floor

  • Tiling - 3rd floor bathrooms & kitchens

  • Fire curtain installation, 3rd floor apartments

  • Paving and stones to roof

  • Mechanical pipework installation in atrium

Block B

  • Perimeter brickwork, 2nd floor

  • Mechanical first fix, ground floor

  • High level mechanical services installation, 4th floor

  • Brickwork, 5th floor

  • Internal walls, 6th floor

  • Scaffold bridge to 4th floor roof area

Block C

  • Sofit installation & plant connections to lower ground floor plantroom

  • Brickwork, 2nd & 3rd floor

  • Lift installation ongoing

  • Ceiling & corridor wall closures & plastering

  • Snagging & inspection of high-level services, 3rd floor

  • Pitched roof covering to 3rd/4th floor

  • Insulation to lower roof (3rd floor)

Otto Close

  • Brickwork & scaffold ‘birdcage’, houses 1-4

  • Roof covering & zinc to dormas, houses 5-7

  • Blockwork for 2nd floor, houses 8-11

  • Possible scaffold delivery - see below.

Deliveries

  • There is possibly another scaffold delivery next week which would need a road closure for up to 2 hours at Otto Close. We will send notification of the date if this is confirmed.

  • We are awaiting confirmation of when the smaller crane will be moved. This is provisionally booked in for Saturday 1 March and would require a temporary road closure whilst it is dismantled. We will notify you of the date, duration and areas affected as soon as we have the information.

Security

  • The night security guard remains on site and the new phone is set up. If you have any issues overnight or over the weekend, please call: 07759 833 036


If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best Wishes,

The Sydenham Hill Project Team

 

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

 For site emergencies, please contact:

Andrew Neary 07436 049 480

Hannah Morgan          07769 306 933

Hamid Vafaeifard        07587 103 467

Dion King                     07901 737 269

Laury Jancauskas         07502 600 834

Security 07759 833 036