Dear Neighbour,
Please find below the activities that are scheduled to take place from the week commencing Tuesday 27 August 2024 in connection with the Sydenham Hill Estate Redevelopment Project. Please note, no works will be occurring on Monday 26 August, due to the bank holiday.
Tuesday 27 - Friday 30 August
Block A
External sheathing boarding in progress
Window installation on 1st and 2nd floors ongoing
Scaffolding and monoflex ongoing
Internal mechanical fittings in progress
External façade ongoing
Blockwork to internal walls ongoing
Roof truss installation ongoing
Waterproofing ongoing
Block B
Building structure for concrete on the 6th floor ongoing
Metsec on ground and 1st floors in progress
Substation installation
Internal mechanical fittings in progress
Building structure for the 5th Floor ongoing
Service trenches for water mains installation in sections. Meter installation connection from Thames Water due imminently; road closure for Thames Water works rescheduled to October*
Scaffolding from ground floor to 3rd floor ongoing
*Please note that the date subject to change, depending on availability
Block C
Roof overruns, upstands, and waterproofing ongoing
Stair core installation in progress
External sheathing boarding in progress
Internal mechanical fittings in progress
Scaffolding from 1st to 4th floors ongoing
Metsec on 1st and 2nd floors ongoing
External façade ongoing
Otto Close
Service trench excavation, located at junction with Kirkdale – set to be finished early September.
Electrical cable installation
Backfilling service trench
Mains water trench excavation
Laying mains water pipe
Rainwater pipe drainage connection works to front of the houses
Scaffold matt works
Clearing materials off site
Substructure brickwork works
Waterproofing to substructure brickwork
Internal blockwork ongoing
Saturday 31 August (08.00 – 13.00)
Continuation of works listed above
Noisy works
Plant movement (excavators and dumpers)
Deliveries
Muck removal lorries in and out of main gate
Concrete lorries in and out of the delivery gate
Transformer being delivered for substation installation
Note/Future works
We have upgraded our security system to monitor night-time activity on-site, which now includes an alarm and an automated voice alert in the event of any intruders. While we hope such incidents do not occur, it is essential that these measures are implemented to ensure public safety
Any extensions to site working hours will continue to be communicated in advance through Planning and CommComm, respectively.
Regarding Otto Close works, please be advised that a partial road closure will be in place for the duration of service enabling works.Access to Otto Close will be maintained at all times
If you have any queries, please contact us on info@sydenhamhillproject.com
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact:
Andrew Neary 07881 023 254
David Olatunji 07340 379 305
Hannah Morgan 07769 306 933
Laurynas Jancauskas 075025 600 834
Best Wishes,
The Sydenham Hill Project Team