Dear Neighbour,
Please find below the activities that are scheduled to take place from the week commencing Monday 10 March 2025 in connection with the Sydenham Hill Estate Redevelopment Project.
Monday 10 - Friday 14 March; Saturday 15 March (08.00 - 13.00)
Block A
Brickwork snagging
Scaffold Strike & window cleaning 1st & 2nd floor
Staircase painting & conduit install
Plastering & boarding of corridors & ceilings
Snagging & finals to ground floor apartments
Decoration of 1st, 2nd & 3rd floor apartments
Appliance delivery & installation, 1st floor
Vaulted ceiling boarding, 3rd floor
Electrical installation in atrium
Gable brickwork, 4th floor
Installing cladding to roof plant area
Block B
Brickwork, 3rd floor perimeter & 5th floor
Mechanical & electrical sign off, ground floor apartments
Drylining, 1st & 2nd floor
Pipe lagging, 3rd floor
High level mechanical services installation, 4th & 5th floor
Roof truss installation to 4th floor roof
Brickwork, 5th floor
Felt & batton to 6th floor roof
Block C
Plant connections in plantroom
Brickwork, 3rd floor
Second fix joinery & M&E, lower ground floor
Ceiling grid & corridor wall closures & plastering, 1st - 3rd floor
Completing tiling to lower roof
Otto Close
Roof truss & dorma installation, houses 1-4
Roof covering & gable wall installation, houses 5-7
Internal scaffold adaption, houses 8-11
Future works/deliveries
The smaller crane is now due to be removed on Saturday 15 March.
If you have any queries, please contact us on info@sydenhamhillproject.com
Best Wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact:
Andrew Neary 07436 049 480
Hannah Morgan 07769 306 933
Hamid Vafaeifard 07587 103 467
Dion King 07901 737 269
Laury Jancauskas 07502 600 834
Security 07759 833 036