Dear Neighbour,
Please find below the activities that are scheduled to take place from the week commencing Monday 9 September 2024 in connection with the Sydenham Hill Estate Redevelopment Project.
Monday 9 - Friday 13 September
Block A
Internal walls – ground floor & level 2
Mechanical and electrical services on Level 1
Floor screed level 1
Windows sealant level 3
Brickwork on level 1
Roof truss installation
Roof waterproofing works
Block B
External walls boarding ground floor
Metal framework forming external walls on the 2nd floor
Installation of pre-formed staircase
External works to facilitate the meter installation by Thames Water. *
Scaffold erected around the perimeter of the building to allow access for the external finishes
Concrete pouring for the level 5 floor slab
Installing reinforcement ahead of concrete for level 6
Block C
Internal walls – lower ground floor and ground floor
Window installation
Installation of internal handrails to the stair case
Boarding to the external frame of the building
External brickwork on the lower ground floor
Otto Close
Water service connections works ongoing – near to completion *
External brickworks, plots 1-4
External waterproofing, plots 5-11
Internal blockwork, plots 5-7
Commence steel column and beam install, plots 5-11 *See note below
Saturday 14 September (08.00 – 13.00)
Continuation of works listed above
Noisy works
Plant movement (excavators and dumpers)
Fixing of metal frame work to form external walls (a different cutting technique is now being used to reduce noise)
Deliveries
Muck removal lorries in and out of main gate
Concrete lorries in and out of the delivery gate
Note/Future works
Regarding Otto Close works, please be advised that a partial road closure will be in place for the duration of service enabling works. Access to Otto Close will be maintained at all times
When the steels for the top plots at Otto Close need to be lifted in, we will need to close the pathway to Lammas Green for safety purposes. This will take place on either Monday 9th or Tuesday 10th September and will take no longer than 2 hours. We will ensure it is not during school drop off/pick up times and traffic marshalls will be monitoring the road and pathway.
Thames Water works: This will require a road closure (Sydenham Hill) for the final connection to the site which is currently planned for 2 October. We will provide further details of any traffic diversions in due course.
If you have any queries, please contact us on info@sydenhamhillproject.com
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact:
Andrew Neary 07881 023 254
David Olatunji 07340 379 305
Hannah Morgan 07769 306 933
Laurynas Jancauskas 075025 600 834
Best Wishes,
The Sydenham Hill Project Team