Sydenham Hill Estate Weekly Works - w/c Monday 8 January 2024

Dear Neighbour,

Please find below the activities that are scheduled to take place from the week commencing Monday 8 January 2024 in connection with the Sydenham Hill Estate Redevelopment Project.

Monday 8 January - Friday 12 January   

  • Pile cropping to Block A

  • Pile caps to Block C

  • Delivery road remediation works

 Saturday 13 January - Sunday 14 January

  • No works will take place

Noisy works

  • Plant movement (excavators and dumpers)

 

Deliveries

  • Muck away lorries in and out of main gate

 

 Note

  • Electricians will be on site this weekend by the ball court to look at re-wiring the Otto Close area to fix the external lighting issues. This work may take some time – we will share updates when we get them.

If you have any queries, please contact us on info@sydenhamhillproject.com

 

With best wishes,

 

The Sydenham Hill Project Team

 

 

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

For site emergencies, please contact Lovell on 020 8731 3800 (0800 030 4690 out of hours)

Alternative numbers:

  • David Olatunji 07340 379305

  • Peter Trainer 07779 992854