Sydenham Hill Estate Weekly Works - w/c 15 January 2024

Dear Neighbour,


Please find below the activities that are scheduled to take place from the week commencing Monday 15 January 2024 in connection with the Sydenham Hill Estate Redevelopment Project.

Monday 15 January - Friday 19 January

  • Pile cropping to Block A

  • Ground Beams to Block A and Block C

  • Drainage works, Block A

  • Pile caps to Block C

  • Lift shaft, Block C

  • Tower crane 2 (TC2) base being built

Saturday 20 January – Sunday 21 January

  • No works will take place

Noisy works

  • Plant movement (excavators and dumpers)

Deliveries

  • Muck away lorries in and out of main gate

Note

  • Please note that we have a fire drill during the daytime on Friday 19 January so you may hear the alarm.

  • We apologise for the alarm that went off early on Thursday morning due to a faulty battery. This has been fixed, but if this should happen again, please contact us using the numbers below. Laury Jancauska (07502 600 834) would be the best person to contact first.


If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best wishes,

The Sydenham Hill Project Team

 

 General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

For site emergencies, please contact Lovell on 020 8731 3800 (0800 030 4690 out of hours)

Alternative numbers:

  • David Olatunji 07340 379305

  • Peter Trainer 07779 992854

  • Laury Jancauska 07502 600834

Plan showing Blocks A, B & C