Sydenham Hill Estate Weekly Works - w/c 7 May 2024

Dear Neighbour,


Sydenham Hill Estate Weekly Works Update:  w/c Tuesday 7 May 2024

 

Please find below the activities that are scheduled to take place from the week commencing Tuesday 7 May 2024 in connection with the Sydenham Hill Estate Redevelopment Project.

 

Tuesday 7 - Friday 10 May (no work on Bank holiday Monday 6 May)

 Block A:          

  • Building the structure to hold the second floor.

  • Perimeter drainage installation

Block B:         

  • Cutting down concrete to foundation piles.

  • Steelwork to concrete floor

  • Drainage installation and waterproofing                    

Block C:          

  • Building the structure to hold the concrete for the first floor

  • Steel work for the structure

     

Otto Close:     

  • Boundary hoarding line works - by steps from alleyway to Lammas Green - *See note/diagram below

  • Reduce level dig to attenuation tank

     

Saturday 11 May

Blocks A/B/C: 

  • Material re-organisation

  • Drainage & decking installation

  • Steel fixing

Otto Close:      TBC

Noisy works

• Plant movement (excavators and dumpers)

Deliveries

• Muck removal lorries in and out of main gate

• Concrete lorries in and out of the delivery gate

Note

  • Further to previous notifications relating to works to the manholes/sewer connections in Otto Close, these are on hold whilst we await a temporary works permit.

  • The repairs to the damaged railings in Otto Close will take place from Wed 8 May. The area will be isolated and signage diversion will be in place.

  • Works will continue on the hoarding line by the lower steps from the alleyway to Lammas Green. Pedestrian access will be diverted around the lower steps of the alleyway to the zig-zag route. Please see diagram in red below – the red area will be fenced off, and access will be via the blue arrows. This diversion will be in place until Friday 10 May.

Plan showing diversion route during hoarding line works

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best wishes,

The Sydenham Hill Project Team

 

 General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

For site emergencies, please contact Lovell on:

  • Andrew Neary 07881 023 254

  • David Olatunji 07340 379305

  • Laury Jancauska 07502 600834

  • Peter Trainer 077779 992854