Monday 5 – Friday 9 February
Pile cropping to Block A, Block B & Block C
Pile caps to Block A & Block C
Ground Beams to Block A & Block C
Drainage works at Block A & Block C
Lift core at Block A & Block C
Drainage works for Otto Close starting by 23 Lammas Green to include surveys, vegetation clearing and Heras fencing.
Saturday 10 – Sunday 11 February
No works will take place
Noisy works
Plant movement (excavators and dumpers)
Deliveries
Muck away lorries in and out of main gate
Concrete lorries in and out of the delivery gate
Note: Fence on Sydenham Hill behind the temporarily relocated bus stop:
Further to the letter sent by CoL on 14 December 2023 proposing a fence to deter anti-social behaviour, we will be proceeding with the installation of the fence in w/c 5 February, which should take approximately 1 week.
Save the Date
We will be holding our next Meet the Contractor Event on Wednesday 21st February at 6.30pm at Lammas Green Community Hall to give you a construction update and answer any questions you may have. We hope you will be able to join us.
If you have any queries, please contact us on info@sydenhamhillproject.com
Best wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact Lovell on 020 8731 3800 (0800 030 4690 out of hours)
Alternative numbers:
David Olatunji 07340 379305
Peter Trainer 07779 992854
Laury Jancauska 07502 600834