Sydenham Hill Estate Weekly Works - w/c 5 February 2024

Dear Neighbour,

Dear Neighbour,

 

Please find below the activities that are scheduled to take place from the week commencing Monday 5 February 2024 in connection with the Sydenham Hill Estate Redevelopment Project.

 

Monday 5 – Friday 9 February    

  •  Pile cropping to Block A, Block B & Block C

  • Pile caps to Block A & Block C

  • Ground Beams to Block A & Block C

  • Drainage works at Block A & Block C

  • Lift core at Block A & Block C

  • Drainage works for Otto Close starting by 23 Lammas Green to include surveys, vegetation clearing and Heras fencing.

 

Saturday 10 – Sunday 11 February 

  • No works will take place

 

Noisy works

  • Plant movement (excavators and dumpers)

 

Deliveries

  • Muck away lorries in and out of main gate

  • Concrete lorries in and out of the delivery gate

Note:   Fence on Sydenham Hill behind the temporarily relocated bus stop:

  • Further to the letter sent by CoL on 14 December 2023 proposing a fence to deter anti-social behaviour, we will be proceeding with the installation of the fence in w/c 5 February, which should take approximately 1 week. 

Save the Date

  • We will be holding our next Meet the Contractor Event on Wednesday 21st February at 6.30pm at Lammas Green Community Hall to give you a construction update and answer any questions you may have.  We hope you will be able to join us.

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best wishes,

The Sydenham Hill Project Team

 

 General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

For site emergencies, please contact Lovell on 020 8731 3800 (0800 030 4690 out of hours)

Alternative numbers:

  • David Olatunji 07340 379305

  • Peter Trainer 07779 992854

  • Laury Jancauska 07502 600834