Sydenham Hill Estate Weekly Works - w/c 29 January 2024

Dear Neighbour,


Please find below the activities that are scheduled to take place from the week commencing Monday 29 January 2024 in connection with the Sydenham Hill Estate Redevelopment Project.

Monday 29 January - Friday 2 February    

  • Pile cropping to Block A and Block B

  • Ground Beams to Block A and Block C

  • Drainage works at Block A

  • Pile caps to Block C

  • Lift shaft, Block C

  • Tower crane 2 (TC2) up and operational

Saturday 3 February - Sunday 4 Februar

  • No works will take place

Noisy works

  • Plant movement (excavators and dumpers)

Deliveries

  • Muck away lorries in and out of main gate

  • Concrete lorries in and out of the delivery gate

Save the Date

  • We will be holding our next Meet the Contractor Event on Wednesday 21st February at 6.30pm at Lammas Green Community Hall to give you a construction update and answer any questions you may have.  We hope you will be able to join us.

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best wishes,

The Sydenham Hill Project Team

 

 General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

For site emergencies, please contact Lovell on 020 8731 3800 (0800 030 4690 out of hours)

Alternative numbers:

  • David Olatunji 07340 379305

  • Peter Trainer 07779 992854

  • Laury Jancauska 07502 600834

Plan showing Blocks A, B & C