Sydenham Hill Estate Weekly Works Update: w/c Monday 7 October 2024

Dear Neighbour,

 

Please find below the activities that are scheduled to take place from the week commencing Monday 7 October 2024 in connection with the Sydenham Hill Estate Redevelopment Project.

Monday 7 - Friday 11 October

Block A

  • Brickwork to 1st & 2nd floor

  • Brickwork to main entrance atrium between blocks A & B

  • Internal walls plasterboard, 2nd floor

  • Floor screeding, 3rd floor

  • Mechanical & electrical installation - ground floor & 1st floor

  • Roof waterproofing works

  • Felt & batten to pitched roof ready for tiling

  • Scaffolding & monoflex

Block B

  • Clearing of materials by framework contractor

  • Hoist installation to transport materials between floors

  • Scaffolding installation to perimeter

  • Brickwork, ground floor

  • External boarding, 1st floor

  • Windows installation, 1st floor

  • Mechanical & electrical installation to generator room

  • Installation of remaining stacks through the building

Block C

  • Internal walls, lower ground floor and high level mechanical & electrical services

  • Electrical installation to riser ground floor to 3rd floor

  • Party walls, 1st floor

  • Window installation, 3rd floor

  • Roof truss installation & waterproofing

Otto Close

  • External brickworks, plots 1-4

  • Internal blockwork, plots 5-11

  • External brickwork, plots 5-7 to commence

  • Scaffolding,plots 1-4

Saturday 12 October (08.00 – 13.00)

  • Continuation of works listed above

 

Noisy works

  • Plant movement (excavators and dumpers)

Deliveries

  • Muck removal lorries in and out of main gate

  • Concrete lorries in and out of the delivery gate

Note/Future works

  • Safety notice: Please ensure that all traffic signs and barriers aimed at passing pedestrians are observed at all times. Marshalls are on site monitoring all construction traffic, and we request that you follow their instructions, particularly if you are with children, for your and their own safety.

  • Thames Water works: The new connection from Thames Water is planned to commence 14 October and is planned to complete withing nine days. Thames Water have applied for a road closure on Sydenham Hill for these works and we will share further information when we receive it from them.

If you have any queries, please contact us on info@sydenhamhillproject.com

 

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

For site emergencies, please contact:

Andrew Neary             07436 049 480

Hannah Morgan          07769 306 933

Laurynas Jancauskas  075025 600 834

Hamid Vafaeifard 07587 103 467

Best Wishes,

The Sydenham Hill Project Team