Sydenham Hill Estate Weekly Works Update: w/c Monday 30 September 2024

Dear Neighbour,

 

Please find below the activities that are scheduled to take place from the week commencing Monday 30 September 2024 in connection with the Sydenham Hill Estate Redevelopment Project.

Monday 30-September - Friday 4 October

Block A

  • Mechanical & electrical installation, ground floor

  • Brickwork continues to 1st floor

  • Internal walls plasterboard, 2nd floor

  • Floor screeding, 3rd floor

  • Roof truss installation & waterproofing

  • Scaffolding & monoflex

Block B

  • Clearing of materials by framework contractor

  • Scaffolding installation/adaptations, perimeter & 2nd floor

  • Brickwork, ground floor

  • Blockwork to generator room

  • External boarding, 1st floor

  • Windows installation, 1st floor

  • Internal staircase installaion

  • Building structure to hold concrete on 6th floor

  • External works/trenches to facilitate the meter installation by Thames Water *

Block C

  • Internal walls, lower ground floor

  • Ground floor party walls & screed flooring

  • Party walls, 1st floor

  • Window installation, 3rd floor

  • Roof truss installation & waterproofing

Otto Close

  • External brickworks, plots 1-4

  • Internal blockwork, plots 5-11

  • Scaffolding,plots 1-4

Saturday 5 October (08.00 – 13.00)

  • Continuation of works listed above

 

Noisy works

  • Plant movement (excavators and dumpers)

Deliveries

  • Muck removal lorries in and out of main gate

  • Concrete lorries in and out of the delivery gate

Note/Future works

  • Safety notice: Please ensure that all traffic signs and barriers aimed at passing pedestrians are observed at all times. Marshalls are on site monitoring all construction traffic, and we request that you follow their instructions, particularly if you are with children, for your and their own safety.

  • Thames Water works: This will require a road closure (Sydenham Hill) for the final connection to the site which is currently planned for October. We will provide further details of any traffic diversions in due course when these are confirmed by Thames Water.

If you have any queries, please contact us on info@sydenhamhillproject.com

 

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

For site emergencies, please contact:

Andrew Neary             07881 023 254

Hannah Morgan          07769 306 933

Laurynas Jancauskas  075025 600 834

Hamid Vafaeifard 07587 103 467

Best Wishes,

The Sydenham Hill Project Team