Dear Neighbour,
Please find below the activities that are scheduled to take place from the week commencing Monday 31 March 2025 in connection with the Sydenham Hill Estate Redevelopment Project.
Monday 31 March - Friday 4 April; Sat 5 April (08.00 - 13.00)
Block A
Brickwork snagging
Rainwater connections to balconies
Ground floor entrance & atrium area - closing walls
Staircase conduit install nearly complete
Mechanical riser door installation
Finishing to corridors & ceilings
Snagging & finals to all apartments
Gable brickwork, 4th floor
Installing cladding to roof plant area
Block B
Brickwork, 4th & 5th floor perimeter
Mechanical & electrical sign off, ground floor apartments
Drylining & ceiling closures, 1st & 2nd floor
Plastering to 1st & 2nd floor apartments
Mechanical services lagging & sign off, 4th & 5th floor
High level mechanical service installation & testing, 6th floor
Felt & batten to 7th floor roof
Waterproofing to gutter
Block C
Plant connections in plantroom
Brickwork, 3rd & 4th floor
Mastic to external windows & movement joints
Tiling, 1st & 2nd floor apartments
Kitchen installations, 2nd floor
Ceiling grid, corridor wall closures & plastering, 3rd floor
Ridge tile installation to roof
Cladding installation to roof
Otto Close
Roof covering & dorma installation ongoing, houses 1-4
Roof tiling, staircase installation & ground floor screen, houses 5-7
Brickwork & blockwork to gable walls & roof truss, houses 8-11
Deliveries
There are no planned large deliveries. There will be a screed lorry delivering the screed on Wednesday but this is not planned to block the road
Notes/Future works
The works to move the fuse board from the garages which is hoped will resolve the issues with the external lighting on Otto Close is now due to take place from Monday 31 March.
Meet the Contractor Events
Save the date for Lovell’s Easter Egg hunt on Tuesday 8 April, meet 2pm at the ball court. All ages welcome!
If you have any queries, please contact us on info@sydenhamhillproject.com
Best Wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact:
Andrew Neary 07436 049 480
Hannah Morgan 07769 306 933
Hamid Vafaeifard 07587 103 467
Dion King 07901 737 269
Laury Jancauskas 07502 600 834
Security 07759 833 036