Sydenham Hill Estate Weekly Works - w/c 29 July 2024

Dear Neighbour,


Please find below the activities that are scheduled to take place from the week commencing Monday 29 July 2024 in connection with the Sydenham Hill Estate Redevelopment Project.

Monday 29 July – Friday 2 August

Block A:

  • External sheet boarding

  • Scaffolding & monoflex

  • External façade

  • Blockwork to Internal wall

  • Window install - 1st floor & 2nd floor

  • Finishing to the concrete framework on the roof

  • Lifting in of pre-cast concrete stairs - Fri 2 August *see note

Block B:

  • Building the structure to hold the concrete for 4th floor

  • Scaffolding

  • Perimeter drainage & service trenches

  • Retaining wall

Block C:

  • Finishing to the concrete framework on the roof

  • Scaffolding - 1st to 4th floor

  • Metal framework - ground floor & 1st floor

  • Civilise earth around retaining wall

Otto Close:

  • Drainage works, including sewage connections on Otto Close - *See note below

  • Concrete beams to rear of first 6 plots

  • Slab preparation work - digging, insultation, waterproofing, steel reinforcing

  • Concrete slab pour on Tuesday 30 July

  • Brickwork starting on the lowest 2 plots

Saturday 3 August (08.00 - 13.00)

  • Continuation of works listed above

Noisy works

  • Plant movement (excavators and dumpers)

Deliveries

  • Muck removal lorries in and out of main gate

  • Concrete lorries in and out of the delivery gate

  • Pre-cast concrete stairs - Fri 2 August

Note

  • We are continuing with a phased closure to parts of Otto Close to carry out works to the manholes to connect the new sewer to the existing sewer.   Access for vehicles and pedestrians will be retained throughout, but parts of the road will be single file traffic around the fenced-off areas where work will be taking place.  At the end of each day a road plate will be put over the manhole and the barriers will be removed to allow traffic to use the whole road safely.

  • Please note that from Friday 2 August - Friday 9 August, we will need to work until 7pm to bring in the pre-cast concrete stairs for blocks A&C. Other trades will finish by 5pm so that the site is clear for the lifting in of the stairs, which will involve crane lifting and not noisy works.

  • Soft Landscaping proposals: There will be a further online meeting on Wednesday 7 August at 6.30pm, for residents to review the changes agreed at the last meeting. Please refer to separate invitation for details on how to attend.

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best wishes,

The Sydenham Hill Project Team

 

 General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 