Dear Neighbour,
Please find below the activities that are scheduled to take place from the week commencing Monday 29 July 2024 in connection with the Sydenham Hill Estate Redevelopment Project.
Monday 29 July – Friday 2 August
Block A:
External sheet boarding
Scaffolding & monoflex
External façade
Blockwork to Internal wall
Window install - 1st floor & 2nd floor
Finishing to the concrete framework on the roof
Lifting in of pre-cast concrete stairs - Fri 2 August *see note
Block B:
Building the structure to hold the concrete for 4th floor
Scaffolding
Perimeter drainage & service trenches
Retaining wall
Block C:
Finishing to the concrete framework on the roof
Scaffolding - 1st to 4th floor
Metal framework - ground floor & 1st floor
Civilise earth around retaining wall
Otto Close:
Drainage works, including sewage connections on Otto Close - *See note below
Concrete beams to rear of first 6 plots
Slab preparation work - digging, insultation, waterproofing, steel reinforcing
Concrete slab pour on Tuesday 30 July
Brickwork starting on the lowest 2 plots
Saturday 3 August (08.00 - 13.00)
Continuation of works listed above
Noisy works
Plant movement (excavators and dumpers)
Deliveries
Muck removal lorries in and out of main gate
Concrete lorries in and out of the delivery gate
Pre-cast concrete stairs - Fri 2 August
Note
We are continuing with a phased closure to parts of Otto Close to carry out works to the manholes to connect the new sewer to the existing sewer. Access for vehicles and pedestrians will be retained throughout, but parts of the road will be single file traffic around the fenced-off areas where work will be taking place. At the end of each day a road plate will be put over the manhole and the barriers will be removed to allow traffic to use the whole road safely.
Please note that from Friday 2 August - Friday 9 August, we will need to work until 7pm to bring in the pre-cast concrete stairs for blocks A&C. Other trades will finish by 5pm so that the site is clear for the lifting in of the stairs, which will involve crane lifting and not noisy works.
Soft Landscaping proposals: There will be a further online meeting on Wednesday 7 August at 6.30pm, for residents to review the changes agreed at the last meeting. Please refer to separate invitation for details on how to attend.
If you have any queries, please contact us on info@sydenhamhillproject.com
Best wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact Lovell on:
Andrew Neary 07881 023 254
David Olatunji 07340 379305
Peter Trainer 077779 992854
Laurynas Jancauskas 07502 600834