Sydenham Hill Estate Weekly Works - w/c 18 March 2024

Dear Neighbour,

 

Please find below the activities that are scheduled to take place from the week commencing Monday 18 March 2024 in connection with the Sydenham Hill Estate Redevelopment Project.

 

Monday 18 – Friday 22 March

  • Block C:

    • Formwork & setting out

    • Steel work for ground floor slab

  • Block A:

    • Ground beams

    • Under slab drainage

    • Blinding for ground floor slab

    • Insulation & waterproofing

    • Drainage Installation

    • Formwork

    • Steel work for ground floor slab

    • Pouring of part of ground floor slab

  • Block B:

    • Pile cropping & pile caps

    • Lift core

    • Steelwork

    • Drainage Installation

  • Ongoing Gate 2 alterations

  • Otto Close:

    • Drainage diversion works by 23 Lammas Green

    • Kingpost install

Saturday 23 – Sunday 24 March 

  • Works will take place at Blocks A-C at Mais House on Saturday 22 March between our permitted hours of 8am – 1pm.  The works carried out include drainage installation, pile cropping, steel fixing, formwork and material reorganisation.

Noisy works

  • Plant movement (excavators and dumpers)

 

Deliveries

  • Muck away lorries in and out of main gate

  • Concrete lorries in and out of the delivery gate

 

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best wishes,

The Sydenham Hill Project Team

 

 General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

For site emergencies, please contact Lovell on 020 8731 3800 (0800 030 4690 out of hours)

Alternative numbers:

  • David Olatunji 07340 379305

  • Peter Trainer 07779 992854