Sydenham Hill Estate Weekly Works - w/c 12 August 2024

Dear Neighbour,

Please find below the activities that are scheduled to take place from the week commencing Monday 12 August 2024 in connection with the Sydenham Hill Estate Redevelopment Project.

Monday 12 - Friday 16 August

Block A:

  • External sheet boarding

  • Scaffolding & monoflex

  • Windows & doors install – 1st – 3rd floor

  • Internal mechanical works

  • Roof truss delivery

  • Roof waterproofing & drylining commencement

Block B:

  • Building the structure to hold the 5th floor

  • Scaffolding

  • Service trench for water mains, BT & Virgin services

  • Civilise earth by Gate 2

Block C:

  • Finishing to the concrete framework on the roof

  • Scaffolding

  • Metal framework – Ground floor & 1st floor

  • Windows install

  • External facade

  • Civilise earth beyond scaffold mat

Otto Close:

  • Drainage works to the last manhole in Otto Close * See note

  • Ground beams to rear of plots 5 to 7

  • Slab preparation work – digging, insulation, waterproofing, steel reinforcing

  • Brickwork and blockwork on first 4 plots

Saturday 17 August (08.00 – 13.00)

  • Continuation of works listed above

Noisy works

  • Plant movement (excavators and dumpers)

Deliveries

  • Muck removal lorries in and out of main gate

  • Concrete lorries in and out of the delivery gate

  • Pre-cast concrete stairs and roof truss delivery and lifting into site by crane.

Note/Future works

  • We have nearly finished works to the manholes in Otto Close to connect the new sewer to the existing sewer. Access for vehicles and pedestrians will be retained throughout, but parts of the road will be single file traffic around the fenced-off areas where work will be taking place. At the end of each day a road plate will be put over the manhole and the barriers will be removed to allow traffic to use the whole road safely.

If you have any queries, please contact us on info@sydenhamhillproject.com

Best Wishes,

The Sydenham Hill Project Team

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00