We are writing to advise you that Lovell formally took site possession on 3 January 2023 and are starting to mobilise in readiness for commencement at the end of this month.

The mobilisation works include:

  • A number of surveys within the buildings and outside related to utilities (for example, small trial pits are required to expose existing services for which a small digger may be required)

  • Removal of the existing security measures (Sitex windows panels) from Mais House

  • Utilities isolation (gas, electricity and water)

  • Site set up, including hoarding around Mais House and Heras fencing around the garages and ball court. This also includes the removal of concrete blocks and existing hoarding at the front of Mais House and the installation of two entrance gates

  • Ecological preparations (bat boxes)

  • Internal clearance of Mais House.

During this mobilisation period you will see an increase in workers on the site in order to carry out the above works.

These mobilisation items do not require planning consent and are separate from the planning conditions being discharged.


Just a reminder that Lovell are holding a Meet the Contractor Event on Thursday 12 January from 5-7pm at Lammas Green Nursery. We look forward to seeing you there. If you are unable to attend, the presentation slides will be shared on this website afterwards.

If you have any queries on the above, please contact us via email at info@sydenhamhillproject.com or call us on 020 7125 0421.