Sydenham Hill Estate Weekly Works Update: w/c Monday 9 December 2024

Dear Neighbour,

 

Please find below the activities that are scheduled to take place from the week commencing Monday 9 December November in connection with the Sydenham Hill Estate Redevelopment Project.

Monday 9 -Friday 13 December; Saturday 14 December (08.00 – 13.00)

 Block A

  • Brickwork continues to 2nd - 3rd floor and perimeter

  • Lift installation commencement

  • Electrical testing to ground floor prior to lights being turned on

  • Joinery installation ground floor

  • Baths & kitchen plumbing, lights & switches - 1st floor

  • Plastering & mist coating, 2nd floor

  • Ceiling grids & plastering, 3rd floor

  • Brickwork and blockwork to roof

Block B

  • Internal blockwork to ground floor

  • Brickwork & internal walls, 1st - 2nd floor

  • Screed to 2nd floor due to complete

  • Internal walls & screed, 3rd floor

  • Windows & ductwork, 4th - 5th floor

  • External boarding, 6th floor

  • Roof blockwork (4th floor) & waterproofing (6th floor)

Block C

  • Brickwork, ground, 1st & 2nd floor

  • Wall insulation & boarding - lower ground floor

  • Mechanical & electrical testing & sign off, ground floor

  • Mechanical & electrical services first fix, 2nd & 3rd floor

  • Roof blockwork (4th floor), pitch roof covering & waterproofing (3rd floor)

Otto Close

  • Blockwork continues, 1st & 2nd floor, houses 1-4

  • Joist installation & blockwork, houses 5-8

  • Scaffold adaptions & joist installations, houses 8-11

 

 Noisy works

  • Plant movement (excavators and dumpers)

Deliveries

  • Muck removal lorries in and out of main gate

  • Concrete lorries in and out of the delivery gate

 

Notes/Future works

  • Meet the Contractor event. It was great to meet those of you who visited the site on Wednesday 4 December - we hope you enjoyed the tour. We will share an update with some photos in our next Residents’ newsletter.

  • UKPN have carried out investigative works on the pavement on Sydenham Hill in relation to the electrical connection to the site. They have advised us that they will need a single lane road closure for further works required. Once they have let us know the date and timeframe we will advise you. We apologise in advance for the disruption this may cause.

  • Lovell Christmas Raffle - Hannah has today delivered tickets to residents for a raffle to win a new television. The draw will take place next week, and Lovell will contact the winner by Friday 13 December. Good Luck!

  • Children’s Christmas Gifts - Lovell are arranging presents for the children on the estate which will be donated by the workforce. The presents will be available for collection from the ballcourt from 4-5pm on Thursday 17 December.

  • The site will close for Christmas on Monday 23rd December and re-open on Thursday 2nd January.

 

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best Wishes,

The Sydenham Hill Project Team

 

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

 For site emergencies, please contact:

Andrew Neary             07436 049 480

Joe Martin                   07967 277 400

Hannah Morgan          07769 306 933

Hamid Vafaeifard        07587 103 467

Dion King                     07901 737 269

Laury Jancauskas         07502 600 834