Sydenham Hill Estate Weekly Works Update: w/c Monday 18 November 2024

Dear Neighbour,

 

Please find below the activities that are scheduled to take place from the week commencing Monday 18 November in connection with the Sydenham Hill Estate Redevelopment Project.

 

Monday 18 – Friday 22 November; Saturday 23 November (08.00 – 13.00)

 

Block A

  • Brickwork to 2nd & 3rd floor

  • Plastering to ground & 1st floor apartments

  • Ceiling grid & boards installation, 1st floor

  • Internal walls

  • Testing of mechanical pipework, 2nd floor

  • Brickwork and blockwork to roof

Block B

  • Scaffolding installation to perimeter – 5th floor

  • Brickwork - ground floor & atrium

  • Internal blockwork to ground floor

  • Internal walls & windows, 1st – 3rd floor

  • Balcony doors 3rd floor

  • External metal & boarding, 5th floor

  • Roof truss installation & waterproofing

Block C

  • Internal blockwork to ground floor

  • Brickwork - 1st floor

  • High level services, lower ground floor & 1st floor

  • Electrical first fix – 2nd floor

  • Internal walls 3rd floor

  • Pitch roof covering & waterproofing

Otto Close

  • Scaffold adaptation to houses 1-4 for blockwork to continue

  • Joist installation to houses 5-7

  • Structural steel installation to first floor

 

 Noisy works

  • Plant movement (excavators and dumpers)

Deliveries

  • Muck removal lorries in and out of main gate

  • Concrete lorries in and out of the delivery gate

 

Notes/Future works

  • Safety notice: Please ensure that all traffic signs and barriers aimed at passing pedestrians are observed at all times.  Marshalls are on site monitoring all construction traffic, and we request that you follow their instructions, particularly if you are with children, for your and their own safety.

  • Meet the Contractor - please see separate invitation to our event on Wednesday 27 November. 

 

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best Wishes,

The Sydenham Hill Project Team

 

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

 For site emergencies, please contact:

Andrew Neary             07436 049 480

Hannah Morgan          07769 306 933

Hamid Vafaeifard        07587 103 467

Dion King                     07901 737 269

Laury Jancauskas         07502 600 834