Dear Neighbour,
Please find below the activities that are scheduled to take place from the week commencing Monday 28 October 2024 in connection with the Sydenham Hill Estate Redevelopment Project.
Monday 28 October - Friday 1 November
Block A
Brickwork to 2nd floor & main entrance atrium and columns between blocks A & B
Internal walls
Mechanical & electrical installation - 1st & 2nd floor
Testing of mechanical pipework, 1st floor
External boarding & windows – 3rd floor
Scaffold adaptation for brickwork
Roof waterproofing works to gutter
Pitched roof tiling
Block B
Scaffolding installation to perimeter
Perimeter brickwork, ground floor
Internal blockwork to ground floor
External boarding 3rd floor
Windows & balcony doors, 1st floor
Electrical installation to generator room
Installation of remaining stacks through the building
Block C
Brickwork to lower ground floor
High level mechanical & electrical services, lower ground floor
Floor screed, 1st - 2nd floor
Internal walls 2nd floor
Pitch roof covering & waterproofing
Otto Close
External brickworks, plots 8-11
Scaffolding,plots 1-7
Floor joist installation, plots 1-4
Steel delivery
Saturday 2 November (08.00 – 13.00)
Continuation of works listed above
Noisy works
Plant movement (excavators and dumpers)
Deliveries
Muck removal lorries in and out of main gate
Concrete lorries in and out of the delivery gate
Steel delivery to Otto Close. The road will be partially blocked whilst this is offloaded. This is expected to take 2-3 hours and we will move the delivery vehicle out of the way when required to allow traffic through.
Note/Future works
Safety notice: Please ensure that all traffic signs and barriers aimed at passing pedestrians are observed at all times. Marshalls are on site monitoring all construction traffic, and we request that you follow their instructions, particularly if you are with children, for your and their own safety.
Recycling/Rubbish collection, Otto Close: We have been informed that recycling bin collections have been missed which could be due to construction lorries blocking the road. Please note that the Lovell traffic marshalls will bring down the bins should the collection not take place before 8am and can also help with emptying the bins if required.
Naming ballot please remember to vote on your choice for the new name of the residential building. Link to ballot here
If you have any queries, please contact us on info@sydenhamhillproject.com
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact:
Andrew Neary 07436 049 480
Hannah Morgan 07769 306 933
Hamid Vafaeifard 07587 103 467
Dion King 07901 737 269
Laury Jancauskas 07502 600 834