Dear Neighbour,
Please find below the activities that are scheduled to take place from the week commencing Monday 16 December in connection with the Sydenham Hill Estate Redevelopment Project.
Monday 16 -Friday 20 December; No works on Saturday 21 December
Block A
Brickwork continues to 3rd floor and perimeter
Lift installation
Second fix electrical installation (lights & switches) - ground floor
Joinery installation ground & 1st floor
Baths & kitchen plumbing, lights & switches - 1st floor
Mist coating, 2nd floor
Ceiling boards & plastering, 3rd floor
Brickwork and blockwork to roof ongoing
Block B
Internal blockwork to ground floor & stair core
Perimeter brickwork, 1st - 2nd floor
Internal walls, 1st - 2nd floor
Screed to ground floor entrance area & 3rd floor
Ductwork & walls, 4th floor
External boarding & windows, 5th - 6th floor
Roof blockwork (4th floor) & waterproofing (6th floor)
Monoflex to scaffolding
Block C
Brickwork, 1st, 2nd & 3rd floor
Wall insulation - lower ground floor
Mechanical & electrical testing & sign off, ground floor
Mechanical & electrical services first fix, 2nd & 3rd floor
Roof blockwork (4th floor), pitch roof covering & waterproofing (3rd floor)
Otto Close
Blockwork continues, 1st & 2nd floor, houses 1-4
Brickwork & blockwork, houses 5-8
Scaffold strike & back propping, houses 8-11
Noisy works
Plant movement (excavators and dumpers)
Deliveries
Muck removal lorries in and out of main gate
Concrete lorries in and out of the delivery gate
Notes/Future works
Children’s Christmas Gifts - Lovell have arranged Christmas presents for the children on the estate which have been donated by their workforce. The presents will be available for collection from the ballcourt on Thursday 17 December from 4-5pm.
Electrical connection works on Sydenham Hill. UKPN have advised us that there is likely to be a single lane road closure on the road from 8 January 2025. We apologise in advance for the disruption this may cause.
The site will close for Christmas on Monday 23rd December and re-open on Thursday 2nd January. During this time there will be someone checking the site for any issues sporadically and there will be a security guard on site 24 hours.
If you have any queries, please contact us on info@sydenhamhillproject.com
Best Wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact:
Andrew Neary 07436 049 480
Joe Martin 07967 277 400
Hannah Morgan 07769 306 933
Hamid Vafaeifard 07587 103 467
Dion King 07901 737 269
Laury Jancauskas 07502 600 834